Project background
The Tashen well program called for drilling and workover equipment rated for deep hole operation. As wells deepen, two variables rise together: downhole pressure and the weight of the drilling string. A mid-range rig rated for 350 tons of hook load will not pull a long, heavy casing string out of a deep hole, and a lighter workover unit will not handle the string weight safely.
The equipment selection had to match the actual depth and the planned tubulars, rather than defaulting to the largest unit available. Over-specifying meant paying for capacity the well did not need; under-specifying meant the rig could not do the job when it arrived on location.